Chapter 9
The Building Campaign of 1824
We came at length to an elevated table-land of
wonderful fertility and
beauty, affording a panoramic prospect very little less in extent
than that of Aetna, and in Ellison's opinion as well as my own, surpassing
the far-famed view from that mountain in all the true elements of
the picturesque.
Edgar Allan Poe
"The Domain of Arnheim"
Report to the Literary Fund
The 1823 report to the Literary Fund approved by the Board of
Visitors
stated that the final "finishings" for the buildings of
accommodation had been
completed in the year since its last report, making the "whole of
these buildings
now in perfect readiness for putting the institution into
opperation." More
importantly, perhaps, the visitors could also report that the
"larger building, for a
Library and other purposes was commenced and has been carried on
with
activity, insomuch that its Walls are now ready to receive there
roof; but that
being of hemispherical form, & pressing outwardly in every
direction, it has been
thought not advisable to place it on the walls, in there present
green State; but
rather to give them time to settle and dry until the ensuing season
. . . whether the
interior work of the building will be finished within the ensuing
year is doubtful."(601)
A year-end calculation by old sachem estimated that $17,642.13 had
been spent
building the hull of the Rotunda, not counting an additional
$3,671.11½ in
unpaid debts.(602) With another
winter in sight and the brickwork still green,
however, little else could be expected to be accomplished in
building the Rotunda
before the spring of 1824.(603)
The proctor, in fact, wanted to cut back on the 15-member slave
labor force hired by the university because it had already made 8
to
900,000 bricks for the building in addition to performing other
rough labor.(604)
(Brockenbrough previously had estimated that 1 molder with the help
of 2 men
and 2 boys could make 60,000 bricks per month, and hence the 15
hands could
make 180,000 per month.)(605)
Jefferson thought that the "great deal of work to be
done yet on the grounds" would require just as many hands for the
next as the
current year, however, and the force remained the same size.(606)
Actually, the claim by the visitors in the report to the
Literary Fund that the
buildings of accommodation were finished was overstated somewhat.
As the site
geared up for the spring resumption of construction work, the
proctor indicated
that gutters and drainpipes as well as "some little painting" and
"some paving &
stone walls to back yards" still remained to be completed. Work on
the
smokehouses planned for each of the pavilions and hotels, as well
as the Venetian
shutters for all the buildings and the "wire lattice work" for the
cellar windows,
had not started yet. The benches and desks for the lecture rooms
also had to be
made, and Brockenbrough estimated the cost for work remaining to be
done on
the buildings, not counting the Venetian blinds and lattice work,
to be at least
$3,000.(607) In the spring of
1824, wagons from Augusta County began to find their
way across the Blue Ridge Mountains, bringing loads of lime for the
brickmakers, and boats and wagons containing nails, screws, glass,
lead,
sandpaper, rope, copper, tin, and iron traveled westward from
Richmond so that
the contractors could complete the unfinished work on the four rows
of buildings
and their dependencies as well as continue their work on the
Rotunda.(608)
Rotunda Gallery
In late March Brockenbrough informed Jefferson that Dinsmore
& Neilson,
without consulting himself or even bothering with a contract for
the job, had
purchased scantling and framed the "upper gallery floor" of the
library and were
set to raise it the next day. Before the work proceeded any
further the proctor
wanted Jefferson to consider some alterations of the interior
design of the
Rotunda that had struck his mind on "seeing the hight of the
gallery" and which
he thought would be an improvement.
The Circumference of the Library room is about 229 feet the
hight of the
wall to the spring of the arch about 18 ft which gives us more than
4,000
superficial feet (including the openings) for book cases without
going to
the upper Gallery which comes immediately under the roof for
another
set of casesand in which case you would conceal a part of the
cieling
very much to the injury of the looks of the room particularly if
the cieling
should be enritched with sunken pannel work &cIn the place of
the
two Galleries I should prefer one on Columns about ten feet high
the
entablature to be above the floor in that case your lower cases
would be
about ten feet high which could be easily come at the upper cases
about
seven feetthe Columns will be smaller and consequently less
expencive
& one entire Gallery will be saved there byif the weather
should be fit
they (D & N) will be raising the floor tomorrow, if you wish
time to
consider on it, you can direct that part of the business to be
delayed
awhile."(609)
Jefferson "maturely" considered the change before rejecting it
a day later as
offering "no advantage" over the original plan. Besides the 4,000
square feet
area intended for "presses below the entablature of the columns,"
Jefferson
explained to the proctor, "we can have another tier of presses
above the
entablature, of one half more of the space. again instead of the
noble perystyle of
the original bearing a proper proportion to the height of vault
above, it proposes
a diminutive one of 10. f. height with a vault of 40. f. above.
the original
peristyle by it's height & projection from the wall has the
advantage of hiding a
portion of the vault of which too much would otherwise be seen.
the panneled
plaistering makes no difficultie because it will be divided by
cross styles into
compartments, and thus adapted to the view." "Messrs. Nelson &
Dinsmore,"
Jefferson added, "should be warned that if they do any thing more
than what was
proposed to be first done, there will be no funds to pay for it."(610)
Gymnasium
One alteration, or evolution, of the original design did take
place, however,
apparently back in the second half of 1823 when Jefferson
experienced his severe
illness. As Martha Jefferson Randolph described it to her daughter
Virginia's
husband Nicholas P. W. Trist in an early April letter, the plan for
the Rotunda
now included a "Gymnasium under cover, under which the young men
may
exercise in bad weather protected equally from the sun & the
rain and the manual
exercise will be a regular branch of their education. this last
improvement, the
Gymnasium, occurred to my Father during a fever that confined him
upon the
sopha. he immediately sent for Mr Brockenbrough and gave him every
direction
onto the plan when he was actually so weak that he could not sit up
to draw it
him self. if you recollect the place you may remember that the
North end of the
lawn is closed by a large rotunda with 2 wide terrace, extending on
each side to
the ranges of buildings, the Pavillions & dormitories. under
these terrace, arched
on both sides and containing a space of 80 feet in length & 30
wide is the
gymnasium." Housejoiner and architect John Neilson actually drew
the north
elevation for the structure, which was incorporated in the
construction during the
spring.(611)
A Quorum Meets
When the 1824 spring meeting of the Board of Visitors began on
Monday 5
April there was nothing for the quorum of Jefferson, Madison,
Cocke, and
Johnson to act upon in regard to the buildings so the board
proceeded to take
"such preparatory measures" as could be taken in regard to bringing
the
university into "opperation with as little delay as practicable,"
by discussing the
"accounts and estimates now rendered by the Bursar and the
Proctor," and by
appointing Virginia attorney Francis Walker Gilmer agent for a
mission to
procure professors from Europe.(612) Those accounts might have
included
Brockenbrough's estimate of the cost of the Rotunda derived from
the contracts
already entered into towards its completion. Those figures
included $10,761.72
for brickwork materials and labor, $10,165 for the Carrara marble
bases and
capitals and their transportation from Leghorn to America, $1,455
for stone
window and door sills, back steps, and terraces, $6,165 for
"Materials principally
Lumber & iron," $2,000 for "Tin & Copper for the roof of
Dome & Portico,"
and $500 for "Glass & Glazing including the sky light." The
total came to
$31,046.72, and Brockenbrough estimated that another $10,000 could
cover the
"Nails, hard ware, painting & Workmans bills."(613) Considering the cost incurred
so far in erecting the hull of the Rotunda and the proctor's vague
projections for
additional costs, it is hard to conceive that anyone on the board
still believed that
the interior of the building could be finished without exceeding
Jefferson's
original 1822 estimate for the building of less than $50,000. If
any of the visitors
complained it failed to get lodged into the record, however. On 6
April the board
was prevented from regathering by a "constant and heavy rain" but
on the 7th the
visitors, now joined by Cabell, reconvened to discuss the curricula
for the various
schools and the purchasing of "Such Books and Apparatus as may be
deemed
most useful for the commencement of the Several Schools in the
University."(614)
The board planned to open the university to students on 1
February 1825,
"taking the intermediate time to procure professors" from Europe,
Jefferson
informed Nicholas P. W. Trist shortly after the visitors' meeting,
and to put the
Rotunda, "the only unfinished building," into a state for use.
(Jefferson also told
Trist that "Charlottesville is building fast.")(615) This long-awaited decision was
made possible by another long-anticipated piece of good luck that
finally had
fallen the university's way during the preceding winter. Senator
Cabell
reluctantly turned over his guardianship of the university's
political affairs in the
General Assembly to General Breckinridge in late November,
expecting to
remain away from Richmond until near the end of the legislative
session,(616) but
unexpectedly (and fortunately) he was able to return "hastily over
stormy rivers,
and frozen roads, to re-join the band of steadfast patriots engaged
in the holy
cause of the University" at his old apartment in Richmond's Eagle
Hotel less than
two weeks later. When he took his seat in the Virginia senate on
3 December
Cabell was made aware immediately that Governor James Pleasants,
Jr., "a man
of great prudence and discretion," was promoting the claims of the
university in
the legislature in "his happiest manner," and that the popular
sentiment was
"decidedly" in favor of removing the university's entire debt.(617) Cabell worked
tirelessly during the session to get bills passed in the General
Assembly remitting
the $180,000 debts incurred in the construction of the buildings of
the university
and granting a gift of $50,000 for the purchase of books and other
"apparatus."
By late January 1824 he had been confined to his room for two
weeks, and his
bed for a week, by an "excruciating rheumatic affection of my head,
contracted
by sleeping near a damp wall."(618) The first victory came through
before the month
ended, however, when the senate unanimously passed a bill sent up
by the House
of Delegates for the remission of the university's debts,(619) and the bonus came on
the last day of the legislative session in March.(620) In fact, Cabell's absence from
the Board of Visitors' meeting until the third day was because of
his attendance in
Washington to lobby President Monroe and the "general government"
of the
United States to settle the interest on the debt it had previously
discharged to the
state of Virginia for the latter's "liberal spirit towards the
government of the
Union" during the War of 1812, and from which the money to pay for
the
remission of the university's debts must come.(621)
Covering the Rotunda
If the weather permitted the members of the Board of Visitors
to inspect the
Rotunda at their April meeting they probably were quite astonished
to see that
Dinsmore & Neilson had framed the building's upper gallery
floor and was
preparing to raise its roof so early in the season.(622) Brockenbrough had written to
D. W. & C. Warwick on 19 March trying to find out how cheaply
the firm could
provide copper or zinc plate for covering the dome and portico but
before he
could receive a reply he presented the board with the heretofore
mentioned
estimate of $2,000.(623) The
proctor also solicited his brother Dr. John
Brockenbrough, Jr., to make inquiries about the price of the metals
and to recruit
someone in Richmond to lay the sheeting. John Brockenbrough
induced
Warwick to sell copper to the university for 26 cents per pound
instead of the
going rate of 35 cents, "provided the quantity be considerable,"
and arranged for
Frenchman Anthony Bargamin, who asked 10 cents the pound to put it
on, to
travel to the site to negotiate a contract with the proctor. "You
cannot have a
better covering than he will make you in this way," Brockenbrough
told his
brother. And instead of gutters, he added, "it will be better, I
think, to extend the
copper over the parapet walls. Zinc might be somewhat cheaper,
provided it
could be procured sufficiently thin, but we Know nothing of it's
durability."(624)
Bargamin, who with his brother George was prominent in the
capitol's
business life, had covered the dome of Richmond's city hall.(625) He "does not
converse very intelligibly in english," the proctor informed
Jefferson when writing
to notify him of Bargamin's impending arrival by stage at
Charlottesville, "if
convenient I Should be glad if you will come up on Thursday morning
to see him
on the subject. the job requires a man well skilled in the working
of metal."(626)
Jefferson, it turned out, was once again too ill to travel to the
university. He
replied to Brockenbrough that "My last ride to the University and
return without
getting off of my horse, with the heat of the day so overcome me
with fatigue
that I could scarcely reach home, and still leaves me so sore and
languid that I
have not been on my horse since, nor shall I be able yet for some
days. if
therefore any consultation is necessary with me I must ask the
favor of yourself
and mr Berjamin to take a ride here at your convenience."(627) The Frenchman
briefly visited the site a couple of weeks before the actual
construction began on
the vault's large wooden ribbed frame, the plan of which was taken,
as
Monticello's dome had been, from Philibert Delorme's Nouvelles
Inventions pour
bien bastir et a petits Fraiz (1576). "I once owned the
book," Jefferson recalled
in the third week of May when writing to General Joseph G. Swift to
borrow a
copy of the volume, "and understood the principles of his
invention, but my
recollection is not particular enough in every thing, our workmen
are strangers to
it, and I fear we may go wrong. if we could be accommodated with
this single
volume it would be of singular service to us."(628) Over the next few weeks, while
the carpenters set up the wooden frame, the tin plate and copper
sheathing
necessary to cover the arch began to come to Bargamin's hand at
Richmond from
New York City, and then was forwarded on to the university.(629) Bargamin tried
to leave the Virginia capitol in mid-June but was delayed, so on 21
June he sent a
workman to the university to "proceed to the preparative Untile my
Arival."(630)
Bargamin reached the site before the beginning of July, however,
and no doubt
the changes in the Rotunda's appearance that had taken place by
capping the
structure during the six-weeks interval greatly stirred his
excitement for the task
that lay before him, for by the end of the summer he had completely
finished
covering the dome. The roof proved "perfectly tight" when tested
by the
September rains but began leaking after workmen perforated the tin
with screws
when fastening the supports to the steps that were raised around
the dome's
base.(631)
Brickwork at the Rotunda
Meanwhile, other building projects besides roof construction
were carried
into effect at the Rotunda. In early May Brockenbrough informed
Jefferson that
the "Portico of the Rotunda & Platform of the back Steps" would
take at least
1,350 square feet of marble flagging, 1,150 for the portico, 160
for the platform,
and 40 for breakage,(632) and
Jefferson placed an order for 1,400 marble squares
two weeks later from Thomas Appleton in Leghorn. Jefferson
informed
Appleton that he was anxious to receive the marble bases and
capitals that he had
ordered the previous fall so that the workmen could "get up our
columns this
season . . . that the columns may have time to settle
before their Capitels are put
on them."(633) Brockenbrough then
sought from Dinsmore & Neilson an estimate
of the amount of lead needed for (in Dinsmore's words) the "leaves
of the
Modellions &c 300 ft superficial @ 5 lbs to the foot," which
the proctor then
ordered, along with two casks of nails and two coils of rope, from
Brockenbrough & Harvie in Richmond.(634) In May the proctor also tried
to
arrange the brickmaking for the upcoming two building seasons. He
requested
John Hartwell Cocke to lend his slave brickmaker, Charles, to the
university for
three months in order to make 2 or 300,000 bricks for the "next
year [1825] if
they should be wanting for any buildings about the University."(635) A few days
later, however, Cocke sent the proctor word that "my engagements
with Charles
will not admit of my sparing him this Season."(636) Brockenbrough then contracted
with John M. Perry to make about 300,000 "hard well shaped bricks
such a
portion of which shall be Column bricks as many as may be required
for the
Rotunda shaped agreeable to a mould to be furnished and such a
portion of
paving bricks as may be wanting for the Rotunda & Gymnasia, and
which shall be
smoth well shaped bricks." Perry also agreed to "take the wood
purchased of
Jesse Lewis & what ever other wood the proctor may have on hand
for the
burning of Bricks at One Dollar per cord on the ground where cut or
two Dollars
delivered at the kiln near the University; the said Perry is to pay
at the rate of
[blank] cents per thousand for the clay that was dug by the
labourers of the
University." Brockenbrough, acting for the University, promised to
pay Perry
$4.50 per thousand bricks and to let Perry have "the use of the
yard, shelters,
clamps &c attached to the Brick yard for the making of the Said
bricks but no
other bricks are to be made or carried from said yard or grounds
for any other
purposed. the Said Shelters, yards, clamps &c to be returned
in good order."(637)
Attic Cisterns
The bricklayers' work on the Rotunda progressed so rapidly
during the spring
of 1824 that by early June the proctor could inform Jefferson that
the firm of
Thorn & Chamberlain was about to begin laying the bricks of the
building's
"attic." Brockenbrough suggested that reservoirs "nearly the depth
of the Attic
and as large in diameter as the space will admit of" be placed in
the two north
corners of the attic so that in case of fire water could be thrown
by "pipes or
hose" to any part of the building beneath the dome. Water for
those reservoirs
could be collected at a reservoir on the university-owned mountain
where
Jefferson hoped to build an observatory and piped from there to the
Rotunda and
other principle buildings. The mountain reservoir, Brockenbrough
contemplated,
should be built of brick or rock and plastered with Roman cement,
in size about
16 feet in diameter and perhaps the same depth, and situated about
50 or 60 feet
above the level of the ground at the buildings so that the weight
of the water
could "propell itself with as much power as an engine would supply
it." The
proctor, well aware that all buildings of his era were particularly
vulnerable to
fire, asserted that a gravity-fed water supply system was both
cheaper and more
efficient than buying a fire engine.(638) The system he proposed to
replace "the
present defective arrangement for the supply of that article
[water]" to the
university offered other benefits as well: the university's
existing cisterns could
be filled occasionally from the pipes and water might be taken from
some stop
cocks for "culinary purposes."
The proctor's suggestion to build reservoirs in the attic of
the Rotunda was
not adopted but Brockenbrough rightly judged that the mountain to
the west
could help to solve the problem of the university's inadequate
water supply.
Previous efforts to provide water had been confined to the local
area of the
university and seemed meager in comparison to the more ambitious
plan which
Brockenbrough now proposed. "at present besides the two cisterns
we have one
pump in operation, two wells walled up ready for pump, one other
well not
entirely finished on west street, I propose puting another between
Pavilions 4 &
6to the south we have a fine Spring about two hundred yards from
the
buildings." Before going to any "great expence" in pursuing his
scheme,
however, Brockenbrough recommended that the university should
purchase "the
right of using the water from the Mountain of Capt [John] Perry or
a Slipe of
land including the spring the latter would be preferable as thereby
we should
connect the two tracts of Land and give us a road to the Mountain."
The proctor
concluded by giving Jefferson his opinion that the university
should execute his
plan before the coming winter, as the "ensurance on the buildings
would amount
to a much greater sum and one or the other would be prudent."(639) Jefferson
agreed that consolidating the university's two separate tracts of
land by gaining
the 132-acre interjacent tract with the "very bold spring" would be
in the
university's long-term interest but withheld pressing Perry about
the matter lest
the carpenter ask an unreasonable price. Perry felt obliged to
sell the land in the
spring of 1825 and the university purchased it for $50 an acre.(640)
Piper Tract
During the summer and fall of 1824 Perry also was involved in
the
university's negotiation and purchase (for about $450) of a
four-acre tract of land
lying immediately to the north of the Rotunda on the Three Notch'd
Road. The
tiny tract was clipped off a larger tract owned by Daniel A. Piper,
who had
installed the gutters and drain pipes at Pavilions I, IV, VI, VII,
and repaired the
pipes at Pavilion III, and his wife Mary A. Frances, who had sold
an adjacent
tract to the university the preceding April.(641) The Three Notch'd Road, which
ran
from Charlottesville to Rockfish Gap and which served as the outer
boundary for
the April purchase, passed by the university in a more or less
northwest to
southeast direction. The new agreement with the Pipers permitted
Jefferson to
re-establish the bed of the public road along the new outlying
boundary line,
causing it to pass parallel to the northern side of the university
(see appendix
G).(642)
The Proctor is Busy
While the executive committee contemplated land deals and
waterworks and
the contractors vaulted the main building and made bricks for
columns, the
proctor supervised the final thrusts (as lay within his power)
aimed at bringing to
completion the initial phases of construction at the university.
In mid-July 1824
stonemason John Gorman began laying the foundation stones for the
"back steps"
(and their retaining walls) on the north front of the Rotunda after
Brockenbrough's laborers excavated and otherwise prepared the earth
on that
steep slope. Brockenbrough sent Jefferson alternate plans for
either concealing
the "ruff work" on the sides of the steps or "facing and coping"
them with stone
but the plans apparently have not survived.(643) Before the summer was over
James
and Samuel Campbell, stonemasons employed by Gorman at the
university,
finished the stonework on the "walls" of the eastern range
hotels.(644) Little
stonework was left at the university after the completion of those
jobs except
setting the marble bases and capitals when they arrived from Italy
in 1825 and
1826.
In early August Brockenbrough ordered sash pulleys and keys
for iron rim
locks from Robert Johnston & Son in Richmond.(645) The firm could not locate the
keys but Peter Johnston found the pulleys when visiting New York on
business in
September, and wagoner Thomas Draffin delivered them (127 pounds in
a barrel)
to the university on 10 November.(646) Also in August, Brockenbrough
sent word
to Andrew Smith, the Boston Glass Manufactory's agent in Richmond,
that the
university was prepared to purchase a large quantity of its best
Boston crown
glass for the window lights of the Rotunda.(647) Wagoner Jacob Mohler delivered
the first shipment to the university in early December, along with
six kegs of
paint and "one half barrel whiting weighing 975 lbs. total."(648) The amount of glass
shipped to the university for the Rotunda eventually exceeded 1,000
sheets
(packed in more than 40 cases), and it was late fall 1825 before
the New England
firm placed its final shipment on board a vessel to embark for the
southward.(649)
With the end of the 1824 building season rapidly approaching,
and the
construction work advancing steadily, the proctor busied himself
with
preparations for the Board of Visitors' 1824 fall meeting. A
statement of the
university's finances that he made for the visitors on the eve of
their meeting
shows that Brockenbrough contemplated the execution of a handful of
minor
tasks while the work on the Rotunda was proceeding. He wanted to
finish
painting Pavilion X and the hotels on the western range and
estimated the cost of
that work at $300. The small "Slipe of Land opposite the Rotunda"
that the
university was negotiating for with Daniel and Mary Piper could be
enclosed with
a brick wall, he thought, for about $450. He considered $300
sufficient "to set
up 8 lecture rooms with benches desk &c," and he calculated
that $250 could
take care of the "Stone walls on east Street & other jobs
fixing pumps &c."(650)
Brockenbrough also prepared a balance sheet of the university's
expenditures to
show the visitors what the cost of building the university had
mounted to so far.
The grand total of $305,664.83 can be broken down generally as
follows:
$109,637.33 for pavilions, $77,430.56 for dormitories, $32,006.85
for hotels,
$25,224.90 for the Rotundaaltogether $244,299.64plus
$61,365.19
for an
assortment of other expenses, including real estate ($8,991.55),
salaries for the
proctor, bursar, clerks, and professors ($3,497.23), labor
($2,936.63), privies
($2,818.63), water works ($1,180.49), and smokehouses ($499.05).(651)
Visitors Draft Regulations
The Board of Visitors' meeting on 4 October was attended by
six of its seven
membersJefferson, Madison, Cabell, Cocke, Breckenridge, and
LoyalJohnson excusing himself on the grounds that he was "quite
unable to
make the ride" on such an "inconvenient journey."(652) The board's first order of
business that Monday was to ratify the university's agreements to
purchase from
the Pipers the two small tracts of land to the Rotunda's north.(653) After passing
other resolutions relative to the institution's finances, the
visitors set to work
formulating the "regulations necessary to constituting governing
and conducting
the institution," a process the board began at its previous spring
meeting. The
regulations drafted by the board included decrees for managing the
usage of the
finished buildings at the university. "The room provided for a
School room in
every Pavilion shall be used for the School of its occupant
professor," the board
resolved, "and shall be furnished by the University with necessary
benches &
tables." And furthermore:
The upper Circular room of the Rotunda shall be reserved
for a
Library. One of its larger eliptical rooms on its middle floor
shall be used
for annual examinations, for lectures to such Schools as are too
numerous for their ordinary schoolrooms, and for religious worship
under the regulations allowed to be prescribed by law. the other
rooms
on the same floor may be used by schools of instruction in drawing,
music, or any other of the innocent and ornamental accomplishments
of
life, but under such instructors as shall be approved and licenced
by the
Faculty.
The rooms in the basement story of the Rotunda shall be,
one for a
Chemical Laboratory: and the others for any necessary purpose to
which
they may be adapted.
The two open apartments adjacent to the same story of the
Rotunda,
shall be appropriated to the Gymnastic exercise and games of the
Students, among which shall be reckoned military
exercises. . . .
Work shops shall be provided, whenever convenient, at the
expense
of the University wherein the students, who chuse, may exercise
themselves in the use of tools, and such mechanical practices as it
is
convenient and useful for every person to understand, and
occasionally to
practice. These shops may be let rent free to such skillful and
orderly
mechanics as shall be approved by the Faculty, on the condition
that they
will permit the use of there tools, instruments, and implements
within the
shop, to such students as shall desire and use the permission
discreetly,
and under a liability for any injury they may do them.(654)
Even the last of these regulations carries Jefferson's strong
imprint. Isaac
Jefferson, a Monticello slave who traveled to Philadelphia with his
master in 1790
when Jefferson became George Washington's secretary of state, said
of Jefferson:
"My Old Master was neat a hand as ever you see to make keys and
locks and
small chains, iron and brass. He kept all kind of blacksmith and
carpenter tools in
a great case with shelves to it in his library, an upstairs
room."(655) Isaac's
observation concerning Jefferson's tools is confirmed in part by
James Dinsmore's
"Memdm of Carpenters tools belonging to Mr. Jefferson" that the
housejoiner
made when leaving Jefferson's employment at Monticello in 1809 (see
appendix
C).(656)
Lafayette Entertained
The board's work required the visitors to reconvene for
another session on
the following day. After resolving to authorize the proctor to
lease the hotels
after mid-November, the board began drafting its annual report to
the Literary
Fund.(657) The report, which
mostly centered around finances, curricula, and
professors, stated that in the course of the present season the
Rotunda "has
received its roof, and will be put into a condition for
preservation and use, altho
its interior cannot be compleated."(658) The incomplete state of the
Rotunda's
interior did not prohibit Jefferson and other area residents from
planning to
entertain the Marquis de Lafayette at a public dinner later that
month, however,(659)
and Jefferson later claimed that upon reflection the building, "in
the unfinished
state in which it then was, was as open and uninclosed, and as
insusceptible of
injury, as the field in which it stood."(660) One visitor to the university
at this time,
however, nineteen-year-old Henry Marshall, who was walking from
Philadelphia
to his home in South Carolina and who later served in the first
Confederate
Congress, apparently thought otherwise. Marshall was so taken with
what he
saw that he described the Rotunda as "decidedly the most elegantly
proportioned
building I ever saw. It is the only public building I have seen in
this country that
is high enough. the professors houses are elegant specimens of
architecture. On
the whole I think they are the most tastiful & elegant
buildings in the U.S. I had
no idea of their extend & splendor."(661)
Construction at the university clearly was nearing completion
even as
workers continued painting and installing window panes throughout
the month of
November.(662) True, on the first
day of winter the "whole scaffolding" surrounding
the Rotunda still could be seen left standing by the workmen as
they awaited
William J. Coffee's shipment of small frieze ornaments.(663) (Coffee shipped the
ornaments to the university in late December.)(664) The agreeably mild fall
weather
allowed workers "to accomplish the repairs and improvements on, and
about the
Buildings; such as plastering leveling the yards and Gardens
conducting or
draining of the water &c; which labour cannot be done so well
after winter."(665)
Chiles Brand's labor account with the university shows that during
December
1824 he earned $4.50 for "White washing 9 rooms at night @ 50¢" in
addition to
the $21.25 he was paid for 17 days of labor work that month.(666) Wagoner
William Crenshaw in mid-January 1825 delivered to the university 19
boxes of
window glass costing $338.56 for the Rotunda that was sent from the
Boston
Glass Manufactory's new Richmond agent, Thomas May.(667) The winter set in,
however, before A. Zigler "the pump man" could finish installing
the water pipes,
delaying the completion of his work until the following
March.(668)
|